Construction of GRP Panels in Tehran wastewater treatment
Employer: Tehran water and wastewater treatment
Location: Tehran- Iran
Year: 1397 (2018)
Production time: 20 working days
The construction of GRP panels in 2018, and with the command of Tehran water and wastewater treatment c, was registered in Sahand Afzar pasargad agenda. In this project the company was responsible for modeling, molding, and production of 12 GRP panels with the length of 610 centimeters.
It should be mentioned that the resin used in the production of Fan Blade is Kahar S65 resin. In this project 5 people did the modeling, molding, and production in 20 working days.